Which of the following activities MUST be completed before developing an IT strategic plan?

The correct answer is A. Review the enterprise business plan. An IT strategic plan must be derived from and fully aligned with the overarching business strategy, making a review of the enterprise business plan the essential first step.

Submitted by tyler.j· Apr 18, 2026Governance of Enterprise IT

Question

Which of the following activities MUST be completed before developing an IT strategic plan?

Options

  • AReview the enterprise business plan
  • BAlign the enterprise vision statement with business processes
  • CDevelop an enterprise architecture (EA) framework
  • DReview the enterprise risk tolerance level

How the community answered

(30 responses)
  • A
    90% (27)
  • B
    7% (2)
  • C
    3% (1)

Why each option

An IT strategic plan must be derived from and fully aligned with the overarching business strategy, making a review of the enterprise business plan the essential first step.

AReview the enterprise business planCorrect

Before developing an IT strategic plan, it is absolutely essential to thoroughly review and understand the enterprise's overall business plan, including its mission, vision, strategic objectives, and goals. The IT strategic plan must be a direct derivative of, and fully aligned with, the business strategy to ensure that IT investments and initiatives support and enable the achievement of business outcomes.

BAlign the enterprise vision statement with business processes

Aligning the enterprise vision with business processes is a specific tactical step within strategic execution, not a prerequisite for developing the IT strategy itself.

CDevelop an enterprise architecture (EA) framework

Developing an enterprise architecture framework is an important part of IT strategy implementation and planning, but it occurs after the high-level strategic direction has been set based on the business plan.

DReview the enterprise risk tolerance level

Reviewing the enterprise risk tolerance level is a critical input to IT strategic planning but is secondary to understanding the core business objectives from the business plan.

Concept tested: IT strategy prerequisites, business-IT alignment

Source: https://learn.microsoft.com/en-us/azure/cloud-adoption-framework/strategy/define-business-outcomes