The correct answer is D: A portfolio describes the organization of related projects, programs, and operations.. A portfolio describes a collection of projects, programs, sub-portfolios, and operations managed together to achieve strategic business objectives.
Submitted by hassan_iq· Apr 18, 2026Governance of Enterprise IT
Question
An organization supports both programs and projects for various industries. What is a portfolio?
Options
- AA portfolio describes all of the monies that are invested in the organization.
- BA portfolio is the total amount of funds that have been invested in programs, projects, and
- CA portfolio describes any project or program within one industry or application area.
- DA portfolio describes the organization of related projects, programs, and operations.
Explanation
A portfolio describes a collection of projects, programs, sub-portfolios, and operations managed together to achieve strategic business objectives.
Common mistakes.
- A. This definition relates to financial investments, not the organizational structure of projects and programs managed to achieve strategic objectives.
- B. This choice partially focuses on funds, which is a component of portfolio management, but it doesn't define the fundamental nature of a portfolio as a collection of organizational initiatives.
- C. A portfolio is not limited to a single industry or application area; it can encompass diverse initiatives aimed at achieving overarching strategic goals across the entire enterprise.
Concept tested. Definition of a portfolio (PMI)
Reference. https://www.pmi.org/learning/library/what-is-portfolio-program-project-management-7389