An enterprise is evaluating a possible strategic initiative for which IT would be the main driver. There are several risk scenarios associated with the initiative that have been identified. Which of…

The correct answer is B. Assess the impact of each risk. When evaluating a strategic IT-driven initiative with identified risk scenarios, the first step to facilitate a decision is to assess the impact of each risk. Understanding the potential consequences of each risk allows for informed prioritization and decision-making regarding…

Submitted by katya_ua· Apr 18, 2026Risk Optimization

Question

An enterprise is evaluating a possible strategic initiative for which IT would be the main driver. There are several risk scenarios associated with the initiative that have been identified. Which of the following should be done FIRST to facilitate a decision?

Options

  • ADefine the risk mitigation strategy.
  • BAssess the impact of each risk.
  • CEstablish a baseline for each initiative.
  • DSelect qualified personnel to manage the project.

How the community answered

(18 responses)
  • A
    6% (1)
  • B
    83% (15)
  • D
    11% (2)

Why each option

When evaluating a strategic IT-driven initiative with identified risk scenarios, the first step to facilitate a decision is to assess the impact of each risk. Understanding the potential consequences of each risk allows for informed prioritization and decision-making regarding the initiative.

ADefine the risk mitigation strategy.

Defining a risk mitigation strategy comes after assessing the risk, as you need to understand the risk's impact and likelihood before planning how to mitigate it.

BAssess the impact of each risk.Correct

Assessing the impact of each risk is the first step because it quantifies or qualifies the potential negative consequences if a risk materializes, which is critical for understanding the severity of each scenario. Before deciding on mitigation or even proceeding, the organization needs to understand 'what if' and 'how bad' each identified risk could be. This assessment facilitates informed decision-making by providing clarity on potential exposures.

CEstablish a baseline for each initiative.

Establishing a baseline for each initiative is important for project tracking and performance measurement, but it doesn't directly address the risk scenarios identified to facilitate the initial strategic decision.

DSelect qualified personnel to manage the project.

Selecting qualified personnel is a project management step that occurs once the decision to proceed with the initiative is made, not a preliminary step for risk evaluation to facilitate the initial decision.

Concept tested: Initial Risk Assessment in Strategic Planning