Which of the following should be the PRIMARY goal of implementing an IT strategic planning process?
The correct answer is D. Translating business needs into IT initiatives. The primary goal of implementing an IT strategic planning process is to ensure that IT efforts directly support and enable the overarching business objectives.
Question
Which of the following should be the PRIMARY goal of implementing an IT strategic planning process?
Options
- ADetermining benefits from IT deployments
- BOptimizing IT resources to drive innovation
- CDirecting business strategy to achieve goals
- DTranslating business needs into IT initiatives
How the community answered
(27 responses)- A4% (1)
- C7% (2)
- D89% (24)
Why each option
The primary goal of implementing an IT strategic planning process is to ensure that IT efforts directly support and enable the overarching business objectives.
Determining benefits from IT deployments is a part of project evaluation and value realization, which follows the strategic planning process, rather than being its primary goal.
Optimizing IT resources to drive innovation is a desired outcome and a part of effective IT management, but it's a subset of aligning IT with business needs, not the primary goal of the planning process itself.
IT strategy should support and enable business strategy, not direct it; the business strategy typically dictates the overall direction for the enterprise.
The primary goal of IT strategic planning is to translate the overarching business needs and objectives into concrete, actionable IT initiatives and strategies. This ensures that IT investments and projects directly contribute to the enterprise's strategic goals, avoiding misalignment and maximizing value delivery.
Concept tested: IT strategic planning goals
Source: https://learn.microsoft.com/en-us/azure/cloud-adoption-framework/strategy/