nerdexam
Isaca

CGEIT · Question #141

An enterprise's internal audit group has scheduled a control review of a payroll system project but has been told to wait until the system is implemented. Which of the following is the GREATEST risk a

The correct answer is C. Increased cost to mitigate deficiencies. Delaying an internal audit control review until a system is fully implemented significantly increases the cost and effort required to mitigate any discovered deficiencies.

Submitted by saadiq_pk· Apr 18, 2026Risk Optimization

Question

An enterprise's internal audit group has scheduled a control review of a payroll system project but has been told to wait until the system is implemented. Which of the following is the GREATEST risk associated with the delay?

Options

  • Adelay in the development of new key performance indicators (KPIs)
  • BContinued dependency on compliant legacy systems
  • CIncreased cost to mitigate deficiencies
  • DLack of adherence to industry best practices

How the community answered

(63 responses)
  • A
    29% (18)
  • B
    6% (4)
  • C
    54% (34)
  • D
    11% (7)

Why each option

Delaying an internal audit control review until a system is fully implemented significantly increases the cost and effort required to mitigate any discovered deficiencies.

Adelay in the development of new key performance indicators (KPIs)

A delay in developing new key performance indicators (KPIs) is a management reporting issue, not the greatest risk associated with the control review itself being delayed.

BContinued dependency on compliant legacy systems

Continued dependency on compliant legacy systems is a pre-existing condition, not a direct risk caused by delaying the audit of the new payroll system.

CIncreased cost to mitigate deficienciesCorrect

When control deficiencies are identified after system implementation, the cost to remediate them is substantially higher due to the need for rework, system modifications, and potential disruption to operational services, compared to addressing issues during earlier project phases. Late detection means issues are more deeply embedded and expensive to extract.

DLack of adherence to industry best practices

Lack of adherence to industry best practices is a potential cause of deficiencies, but the greatest risk of delaying the audit is the cost consequence of finding those deficiencies late.

Concept tested: Risk of delayed control audits in project lifecycle

Source: https://csrc.nist.gov/publications/detail/sp/800-64/rev-2/final

Topics

#Internal Audit#Project Risk#Cost Management#Control Review

Community Discussion

No community discussion yet for this question.

Full CGEIT Practice