CCBA · Question #72

Which of the following is an output of the Identify Stakeholders process?

The correct answer is C. Stakeholder register. The stakeholder register is the key output of the Identify Stakeholders process. It not only contains the names of the project stakeholders but also their goals, expectations, concerns, and other such details. The stakeholder register helps to plan, manage, and communicate with…

Business Analysis Planning and Monitoring

Question

Which of the following is an output of the Identify Stakeholders process?

Options

  • AScope baseline
  • BProject charter
  • CStakeholder register
  • DProject scope statement

How the community answered

(63 responses)
  • A
    3% (2)
  • B
    2% (1)
  • C
    94% (59)
  • D
    2% (1)

Explanation

The stakeholder register is the key output of the Identify Stakeholders process. It not only contains the names of the project stakeholders but also their goals, expectations, concerns, and other such details. The stakeholder register helps to plan, manage, and communicate with the stakeholders effectively and efficiently. The other options are not outputs of the Identify Stakeholders process, but inputs or outputs of other processes. The scope baseline, the project charter, and the project scope statement are all inputs or outputs of the Project Scope Management knowledge area, not the Project Stakeholder Management knowledge area.