CCBA · Question #548
A project manager (PM) is planning the project timelines along with a business analyst (BA), and they come across the task of requirement allocation. The PM wants to know what the dependencies are…
The correct answer is B. Solution approach has been determined. Before allocating requirements, thesolution approach must be determined, as it defines whether requirements will be implementedinternally, externally, or through a hybrid approach. The BABOK® Guide (Chapter 6.1 - Define Solution Approach)states thatrequirement allocation…
Question
A project manager (PM) is planning the project timelines along with a business analyst (BA), and they come across the task of requirement allocation. The PM wants to know what the dependencies are before the requirement allocation task is initiated and seeks the BA's advice. Which of the following is a dependency that the BA will highlight as a prerequisite for requirement allocation?
Options
- ADesign options are available
- BSolution approach has been determined
- CRequirements architecture is approved
- DStakeholders are identified
How the community answered
(21 responses)- A14% (3)
- B76% (16)
- C5% (1)
- D5% (1)
Explanation
Before allocating requirements, thesolution approach must be determined, as it defines whether requirements will be implementedinternally, externally, or through a hybrid approach. The BABOK® Guide (Chapter 6.1 - Define Solution Approach)states thatrequirement allocation depends on understanding how the solution will be developed or acquired. Without this, requirement allocation cannot proceed effectively.