CCBA · Question #511
CCBA Question #511: Real Exam Question with Answer & Explanation
The correct answer is C. Predictive development process. A predictive development process is a type of approach that follows a predefined and detailed plan for delivering the solution, with minimal changes and uncertainties1. A predictive development process is suitable for the initiative that has a short deadline and a regulatory mand
Question
Options
- ACrystal clear development process
- BKanban development process
- CPredictive development process
- DAdaptive development process
Explanation
A predictive development process is a type of approach that follows a predefined and detailed plan for delivering the solution, with minimal changes and uncertainties1. A predictive development process is suitable for the initiative that has a short deadline and a regulatory mandate, as it can help the BA and the stakeholders to ensure that the solution meets the compliance requirements and the schedule constraints. A predictive development process can also help to manage the risks and expectations of the stakeholders, as it provides clear and consistent scope, requirements, and deliverables2. The other options are not the best approaches for the initiative, as they may not be able to handle the complexity and urgency of the project. A crystal clear development process is a type of agile approach that focuses on collaboration, communication, and feedback, with frequent iterations and adjustments3. A Kanban development process is a type of lean approach that visualizes theworkflow, limits the work in progress, and optimizes the flow of value. An adaptive development process is a type of approach that responds to changes and uncertainties, with flexible and iterative planning and
Community Discussion
No community discussion yet for this question.