CCBA · Question #483
The business analysis deliverables went through a formal performance review process. The performance report stated that changes to the business analysis approach must be made in order to maximize…
The correct answer is A. The project manager. The project manager must be consulted regarding the changes to the business analysis approach before they are implemented in this project. The project manager is responsible for planning, executing, monitoring, controlling, and closing the project activities within the…
Question
The business analysis deliverables went through a formal performance review process. The performance report stated that changes to the business analysis approach must be made in order to maximize the project's chances of success. Who must be consulted regarding these changes before they are implemented in this project?
Options
- AThe project manager
- BThe lead developer
- CThe enterprise architect
- DThe subject matter expert
How the community answered
(42 responses)- A90% (38)
- B2% (1)
- C5% (2)
- D2% (1)
Explanation
The project manager must be consulted regarding the changes to the business analysis approach before they are implemented in this project. The project manager is responsible for planning, executing, monitoring, controlling, and closing the project activities within the constraints of scope, time, cost, quality, resources, and risk. The project manager also coordinates with other roles such as business analysts, developers, testers, sponsors, and end users. Therefore, any changes to the business analysis approach must be discussed with the project manager to ensure alignment with the project objectives and plan.
Topics
Community Discussion
No community discussion yet for this question.