CCBA · Question #470
A senior manager wants to know at what stage the business analyst (BA) is with the requirements management process. The BA immediately sends a 600-page document with models and business rules to all…
The correct answer is B. The communication method was inappropriate. The communication method was inappropriate because the BA sent a 600-page document without any summary or explanation to all stakeholders, which is likely to overwhelm and confuse them. The BA should have chosen a more suitable format and level of detail to communicate the…
Question
A senior manager wants to know at what stage the business analyst (BA) is with the requirements management process. The BA immediately sends a 600-page document with models and business rules to all stakeholders. Which best practice did the BA violate in this situation?
Options
- AThe business rules were included
- BThe communication method was inappropriate
- CThe distribution included all project stakeholders
- DThe models were included
How the community answered
(43 responses)- A2% (1)
- B95% (41)
- D2% (1)
Explanation
The communication method was inappropriate because the BA sent a 600-page document without any summary or explanation to all stakeholders, which is likely to overwhelm and confuse them. The BA should have chosen a more suitable format and level of detail to communicate the status of the requirements management process, such as a dashboard or a report. The business rules, the distribution, and the models were not the main issues in this situation.
Topics