CCBA · Question #470

A senior manager wants to know at what stage the business analyst (BA) is with the requirements management process. The BA immediately sends a 600-page document with models and business rules to all…

The correct answer is B. The communication method was inappropriate. The communication method was inappropriate because the BA sent a 600-page document without any summary or explanation to all stakeholders, which is likely to overwhelm and confuse them. The BA should have chosen a more suitable format and level of detail to communicate the…

Business Analysis Planning and Monitoring

Question

A senior manager wants to know at what stage the business analyst (BA) is with the requirements management process. The BA immediately sends a 600-page document with models and business rules to all stakeholders. Which best practice did the BA violate in this situation?

Options

  • AThe business rules were included
  • BThe communication method was inappropriate
  • CThe distribution included all project stakeholders
  • DThe models were included

How the community answered

(43 responses)
  • A
    2% (1)
  • B
    95% (41)
  • D
    2% (1)

Explanation

The communication method was inappropriate because the BA sent a 600-page document without any summary or explanation to all stakeholders, which is likely to overwhelm and confuse them. The BA should have chosen a more suitable format and level of detail to communicate the status of the requirements management process, such as a dashboard or a report. The business rules, the distribution, and the models were not the main issues in this situation.

Topics

#communication approach#stakeholder communication#requirements distribution#best practices