A new contract requires a thorough level of documentation to be developed and maintained with planned phases of reviews and authorized sign offs. Which approach fits this contract?

The correct answer is A. Waterfall. According to the BABOK® Guide, a waterfall approach is a sequential project life cycle that consists of distinct phases, such as initiation, planning, analysis, design, construction, testing, implementation, and maintenance. Each phase has a defined set of activities…

Business Analysis Planning and Monitoring

Question

A new contract requires a thorough level of documentation to be developed and maintained with planned phases of reviews and authorized sign offs. Which approach fits this contract?

Options

  • AWaterfall
  • BAgile
  • CScrum
  • DIterative

How the community answered

(59 responses)
  • A
    90% (53)
  • B
    3% (2)
  • C
    5% (3)
  • D
    2% (1)

Explanation

According to the BABOK® Guide, a waterfall approach is a sequential project life cycle that consists of distinct phases, such as initiation, planning, analysis, design, construction, testing, implementation, and maintenance. Each phase has a defined set of activities, deliverables, and exit criteria that must be completed before moving to the next phase. A waterfall approach is suitable for projects that have a clear and stable scope, well-defined requirements, and minimal changes or uncertainty. In this scenario, a new contract requires a thorough level of documentation to be developed and maintained with planned phases of reviews and authorized sign offs. This implies that the project has a high degree of formality, control, and documentation, which fits the characteristics of a waterfall approach.

Topics

#waterfall methodology#documentation standards#governance#project approach