CCBA · Question #396
An organization prefers to execute projects using an adaptive approach. However, the new project is much more complex than previously executed projects. What will the business analyst (BA) recommend?
The correct answer is B. Review current approach with key stakeholders. Engaging with key stakeholders to review the current adaptive approach allows for a collaborative assessment of its suitability for the new project's complexity. This may lead to modifications or the adoption of different methodologies to ensure project success.
Question
An organization prefers to execute projects using an adaptive approach. However, the new project is much more complex than previously executed projects. What will the business analyst (BA) recommend?
Options
- ASelect an extreme programming approach
- BReview current approach with key stakeholders
- CFollow a predictive approach
- DChoose an agile programming approach
How the community answered
(50 responses)- A12% (6)
- B78% (39)
- C2% (1)
- D8% (4)
Explanation
Engaging with key stakeholders to review the current adaptive approach allows for a collaborative assessment of its suitability for the new project's complexity. This may lead to modifications or the adoption of different methodologies to ensure project success.