CCBA · Question #319
A company is embarking on a software project in a heavily regulated domain. The client expects large upfront planning and detailed documentation for the project. The recommended approach for the proje
The correct answer is B. predictive.. According to the BABOK® Guide, a predictive approach is a business analysis approach that defines the scope, requirements, and designs early in the change initiative lifecycle. This approach is suitable for projects that have a clear and stable vision, well-understood requirement
Question
A company is embarking on a software project in a heavily regulated domain. The client expects large upfront planning and detailed documentation for the project. The recommended approach for the project will be:
Options
- Aadaptive.
- Bpredictive.
- Cwaterfall.
- Dscrum.
How the community answered
(57 responses)- A7% (4)
- B88% (50)
- C2% (1)
- D4% (2)
Explanation
According to the BABOK® Guide, a predictive approach is a business analysis approach that defines the scope, requirements, and designs early in the change initiative lifecycle. This approach is suitable for projects that have a clear and stable vision, well-understood requirements, and a low degree of uncertainty and change. A predictive approach also involves large upfront planning and detailed documentation, which are often required in heavily regulated domains. Therefore, a predictive approach is the recommended approach for the project described in the question.