A business analyst (BA) was asked to send the requirement details to the project manager (PM), director, vice president (VP), and Chief Information Officer (CIO). The BA shares the complete set of req
The correct answer is D. Implement appropriate level of abstraction. According to the BABOK® Guide, one of the tasks of the business analyst (BA) during requirements analysis and design definition is to specify and model requirements. This involves defining and documenting the characteristics and behavior of a solution that meets stakeholder needs
Question
A business analyst (BA) was asked to send the requirement details to the project manager (PM), director, vice president (VP), and Chief Information Officer (CIO). The BA shares the complete set of requirements to the PM and director, while creating a summarized version for the VP and CIO. Which aspect of requirement specification and modeling was the BA performing?
Options
- APerform stakeholder analysis
- BOrganize requirements categories
- CDetermine approval authority
- DImplement appropriate level of abstraction
How the community answered
(15 responses)- A13% (2)
- C7% (1)
- D80% (12)
Explanation
According to the BABOK® Guide, one of the tasks of the business analyst (BA) during requirements analysis and design definition is to specify and model requirements. This involves defining and documenting the characteristics and behavior of a solution that meets stakeholder needs. One of the techniques that can be used for this task is abstraction, which is the process of removing or suppressing details to focus on essential characteristics. By creating a summarized version of the requirements for the VP and CIO, the BA was implementing an appropriate level of abstraction for different audiences and purposes.