CCBA · Question #156
Project Communication Management includes the processes required to.
The correct answer is A. Ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate. Project Communication Management is the knowledge area that covers the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information. It involves planning, managing, monitoring, and…
Question
Project Communication Management includes the processes required to.
Options
- AEnsure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate
- BIdentify, define, combine, unify, and coordinate the various processes and project management
- CManage timely completion of the project.
- DOrganize, manage, and lead the project team.
How the community answered
(28 responses)- A86% (24)
- B4% (1)
- C4% (1)
- D7% (2)
Explanation
Project Communication Management is the knowledge area that covers the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information. It involves planning, managing, monitoring, and controlling the communication activities and deliverables throughout the project lifecycle. Project Communication Management helps to keep the project stakeholders informed, engaged, and satisfied with the project progress and outcomes12. The other options are not correct because: Option B is incorrect. Identifying, defining, combining, unifying, and coordinating the various processes and project management activities with the Project Management Process Groups is the definition of Project Integration Management, not Project Communication Management. Project Integration Management is the knowledge area that covers the processes required to ensure that the various elements of the project are properly coordinated and aligned3. Option C is incorrect. Managing timely completion of the project is the objective of Project Time Management, not Project Communication Management. Project Time Management is the knowledge area that covers the processes required to ensure that the project is completed within the agreed time Option D is incorrect. Organizing, managing, and leading the project team is the responsibility of Project Human Resource Management, not Project Communication Management. Project Human Resource Management is the knowledge area that covers the processes required to ensure that the project has the most effective and efficient human resources.