nerdexam
IIBA

CBAP · Question #535

An automobile manufacturer is undertaking a project intended to modify or replace the company's current timekeeping system. Negative employee reaction to change follows as word of the proposed…

The correct answer is A. Record negative employee reaction as a project risk. Recording negative employee reaction as a project risk is a core BA responsibility, ensuring the concern is formally tracked and can be monitored or mitigated throughout the project lifecycle.

Business Analysis Planning and Monitoring

Question

An automobile manufacturer is undertaking a project intended to modify or replace the company's current timekeeping system. Negative employee reaction to change follows as word of the proposed solution spreads throughout the company. What could a business analyst (BA) do to prevent or reduce employee discontent?

Options

  • ARecord negative employee reaction as a project risk
  • BPropose cultural changes for the organization
  • CReport potential sources of dissent to management
  • DRelay upper management support to stakeholders

How the community answered

(37 responses)
  • A
    81% (30)
  • B
    8% (3)
  • C
    8% (3)
  • D
    3% (1)

Why each option

Recording negative employee reaction as a project risk is a core BA responsibility, ensuring the concern is formally tracked and can be monitored or mitigated throughout the project lifecycle.

ARecord negative employee reaction as a project riskCorrect

A BA is responsible for identifying, documenting, and tracking project risks; negative employee reaction to a change initiative represents a legitimate risk to adoption and project success that belongs in the risk register. Formalizing it as a risk ensures the project team can plan mitigation strategies, such as change management activities, rather than ignoring the discontent. This is within the BA's defined scope and follows established business analysis practice.

BPropose cultural changes for the organization

Proposing cultural changes is a strategic organizational initiative that falls outside the typical authority and responsibility of a BA on a project.

CReport potential sources of dissent to management

Reporting employees as sources of dissent to management is adversarial, damages stakeholder trust, and is not a recognized BA technique for managing resistance to change.

DRelay upper management support to stakeholders

Relaying management support is a communication activity that may help but does not proactively identify or document the risk of employee discontent for tracking and mitigation.

Concept tested: BA risk identification during organizational change

Source: https://www.iiba.org/standards-and-resources/babok/

Topics

#change resistance#risk management#employee discontent#organizational change

Community Discussion

No community discussion yet for this question.