nerdexam
IIBA

CBAP · Question #514

CBAP Question #514: Real Exam Question with Answer & Explanation

The correct answer is C. Risk register. A risk register formally documents the identified risk of incomplete requirements verification along with its mitigation plan, providing the project board with the governance-level assurance that the concern is being actively managed.

Question

Due to the complexity of a project the project board a concerned that the business analyst (BA) will not be able to ensure all requirements are verified. What toed can the BA present to the project board to mitigate their concern?

Options

  • AData model
  • BUse case diagram
  • CRisk register
  • DBusiness analysis checklist

Explanation

A risk register formally documents the identified risk of incomplete requirements verification along with its mitigation plan, providing the project board with the governance-level assurance that the concern is being actively managed.

Common mistakes.

  • A. A data model represents data entities, attributes, and relationships within a system and does not address project governance concerns about the completeness of requirements verification activities.
  • B. A use case diagram illustrates functional interactions between actors and a system; it does not provide a mechanism for documenting, tracking, or mitigating the risk of incomplete requirements verification.
  • D. While a business analysis checklist supports process completeness during execution, it does not formally capture risk ownership, likelihood, impact assessment, or a structured mitigation plan in the way needed to satisfy project board governance concerns.

Concept tested. Risk register for requirements verification governance

Reference. https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Community Discussion

No community discussion yet for this question.

Full CBAP Practice