nerdexam
IIBA

CBAP · Question #394

A business analyst (BA) is planning for an upcoming solution based on a signed contract with a client but has learned that one of the key subject matter experts is unavailable during the first half of

The correct answer is B. Reduce the schedule to coincide with the subject matter expert's availability and reduce the. With a firm contractual deadline and no substitute for the unavailable SME, the BA should compress the analysis schedule into the window when the SME becomes available rather than changing scope or accepting unresolvable risk.

Business Analysis Planning and Monitoring

Question

A business analyst (BA) is planning for an upcoming solution based on a signed contract with a client but has learned that one of the key subject matter experts is unavailable during the first half of the business analysis phase. The project has a tight timeline and firm deadline that is part of the contract. There are no substitutes for the key subject matter expert. How should the BA proceed?

Options

  • AChange the solution scope by removing the subject matter expert's component and obtain
  • BReduce the schedule to coincide with the subject matter expert's availability and reduce the
  • CDocument the contract terms as a risk and adjust the contract costs to plan for the changes/rework
  • DIdentify the missing stakeholder as a risk and recommend an adaptive approach for the analysis

How the community answered

(26 responses)
  • A
    15% (4)
  • B
    73% (19)
  • C
    4% (1)
  • D
    8% (2)

Why each option

With a firm contractual deadline and no substitute for the unavailable SME, the BA should compress the analysis schedule into the window when the SME becomes available rather than changing scope or accepting unresolvable risk.

AChange the solution scope by removing the subject matter expert's component and obtain

Changing the solution scope to remove the SME's component requires a contract amendment and eliminates agreed deliverables, which may not be acceptable to the client.

BReduce the schedule to coincide with the subject matter expert's availability and reduce theCorrect

Reducing the schedule to coincide with the SME's availability means deferring the relevant analysis activities until the second half of the phase when the SME is present, then compressing those activities to still meet the firm deadline. This preserves the integrity of the requirements work by ensuring the right expert is involved without violating the contract or removing components. It is the most realistic option given the constraints of no substitutes and a fixed deadline.

CDocument the contract terms as a risk and adjust the contract costs to plan for the changes/rework

Documenting the contract terms as a risk and adjusting costs does not resolve the scheduling conflict and leaves the BA phase without a critical resource during a defined period.

DIdentify the missing stakeholder as a risk and recommend an adaptive approach for the analysis

Recommending an adaptive approach alone does not solve the constraint because the SME is still unavailable for the first half regardless of methodology, and the firm deadline remains unchanged.

Concept tested: Schedule adjustment for key stakeholder availability constraints

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#BA planning#resource constraints#schedule management#stakeholder availability

Community Discussion

No community discussion yet for this question.

Full CBAP Practice