CBAP · Question #188
Which of the following is a graphical representation of roles and responsibilities of different project team members?
The correct answer is A. RACI chart. A RACI chart is a responsibility assignment matrix that graphically maps project tasks to team members using four roles - Responsible, Accountable, Consulted, and Informed.
Question
Which of the following is a graphical representation of roles and responsibilities of different project team members?
Options
- ARACI chart
- BPareto chart
- CResource histogram chart
- DOrganization chart
How the community answered
(41 responses)- A76% (31)
- B12% (5)
- C7% (3)
- D5% (2)
Why each option
A RACI chart is a responsibility assignment matrix that graphically maps project tasks to team members using four roles - Responsible, Accountable, Consulted, and Informed.
A RACI chart is a graphical matrix used in project management to define and display the roles and responsibilities of each team member in relation to project tasks or deliverables. The four designations - Responsible, Accountable, Consulted, and Informed - ensure clarity around who does the work, who owns it, who provides input, and who is kept updated.
A Pareto chart is a quality management tool that displays defects or issues in descending order of frequency to identify the most significant causes, not a representation of team roles and responsibilities.
A resource histogram chart shows the quantity of resources allocated over time, focusing on workload distribution rather than defining specific roles and responsibilities for each team member.
An organization chart shows the hierarchical reporting structure of an organization, not the specific task-level roles and responsibilities assigned to team members on a project.
Concept tested: RACI chart roles and responsibilities matrix
Source: https://www.pmi.org/learning/library/make-most-out-raci-chart-8797