Which of the following process groups occurs at the beginning of the project?
The correct answer is C. Initiating. The Initiating process group occurs at the beginning of a project and is used to formally authorize the project and define its high-level scope and objectives.
Question
Which of the following process groups occurs at the beginning of the project?
Options
- AExecuting
- BPlanning
- CInitiating
- DControlling and Monitoring
- EClosing
How the community answered
(32 responses)- B6% (2)
- C84% (27)
- D6% (2)
- E3% (1)
Why each option
The Initiating process group occurs at the beginning of a project and is used to formally authorize the project and define its high-level scope and objectives.
Executing is the process group where the project plan is carried out and deliverables are produced, occurring after planning - not at the beginning.
Planning follows Initiating and involves developing the detailed project management plan, so it is the second process group, not the first.
The Initiating process group is explicitly defined in the PMBOK Guide as the processes performed to define a new project or phase, obtain authorization to start it, and establish initial scope and resources. It is the first process group in the project life cycle, preceding all other groups. Key outputs include the project charter and identification of stakeholders, which set the foundation for all subsequent work.
Monitoring and Controlling runs throughout the project to track performance and implement changes, but it does not mark the beginning of a project.
Closing is the final process group that formally completes the project or phase and occurs at the end, not the beginning.
Concept tested: PMBOK process groups order and Initiating phase