Which of the following defines how the project scope should be created, executed, monitored and controlled, and then validated?

The correct answer is B. Scope management plan. The Scope Management Plan is the document that defines how project scope will be created, executed, monitored, controlled, and validated throughout the project.

Business Analysis Planning and Monitoring

Question

Which of the following defines how the project scope should be created, executed, monitored and controlled, and then validated?

Options

  • AScope variance plan
  • BScope management plan
  • CStaffing management plan
  • DSchedule management plan

How the community answered

(48 responses)
  • A
    2% (1)
  • B
    79% (38)
  • C
    6% (3)
  • D
    13% (6)

Why each option

The Scope Management Plan is the document that defines how project scope will be created, executed, monitored, controlled, and validated throughout the project.

AScope variance plan

Scope variance plan is not a recognized artifact in the PMBOK framework and does not exist as a standard project management document.

BScope management planCorrect

The Scope Management Plan is a subsidiary component of the Project Management Plan that provides guidance on how scope will be defined, how the WBS will be developed, how deliverables will be validated, and how scope changes will be controlled. It governs every phase of scope work from initial definition through formal acceptance, making it the single document that covers all the activities listed in the question.

CStaffing management plan

The Staffing Management Plan (Resource Management Plan) addresses acquiring, developing, and releasing project team members and physical resources, not scope activities.

DSchedule management plan

The Schedule Management Plan defines how the project schedule will be developed and controlled, which is a separate concern from managing project scope.

Concept tested: Scope Management Plan purpose and scope lifecycle coverage

Source: https://www.pmi.org/pmbok-guide-standards

Topics

#scope management plan#project scope#monitoring and control#planning