Which of the following is the process of developing a document that formally authorizes a project or a phase?
The correct answer is C. Develop Project Charter. The Develop Project Charter process produces the document that formally authorizes a project or phase and grants the project manager authority to apply resources.
Question
Which of the following is the process of developing a document that formally authorizes a project or a phase?
Options
- ADefine Scope
- BDevelop Schedule
- CDevelop Project Charter
- DCreate Work Breakdown Structure
How the community answered
(33 responses)- A6% (2)
- B9% (3)
- C82% (27)
- D3% (1)
Why each option
The Develop Project Charter process produces the document that formally authorizes a project or phase and grants the project manager authority to apply resources.
Define Scope develops a detailed description of the project and its deliverables, which occurs after the project has already been authorized.
Develop Schedule analyzes activity sequences and resource estimates to produce a project schedule model, a planning process unrelated to authorization.
Develop Project Charter is the specific PMBOK process that creates the project charter, the document that formally authorizes the existence of a project or a phase. It documents high-level requirements, objectives, and the project manager's authority to use organizational resources. All other initiation activities depend on the charter existing first.
Create Work Breakdown Structure decomposes project deliverables into smaller, manageable components and is a planning process, not an authorization process.
Concept tested: Develop Project Charter process in PMBOK