The correct answer is D. The locations selected on the projects have not been associated to the department.. See the full explanation below for the reasoning.

Question

A customer has set up their department Organizational Breakdown Structure (CBS) and completed the financial settings from the CA Clarity PPM Administration menu. They have also created several departments from the Home menu. However, these new departments are not viewable from the Department CBS browse on projects. Why might this happen?

Options

  • ADepartments have not been associated with a service.
  • BDepartments have not been manually added to the Department CBS.
  • CDepartments have not been assigned a Business Relationship Manager.
  • DThe locations selected on the projects have not been associated to the department.