When you perform an Auto schedule With Publish action:

The correct answer is B. The new schedule replaces the plan of record (POR). See the full explanation below for the reasoning.

Question

When you perform an Auto schedule With Publish action:

Options

  • AA tentative schedule is created.
  • BThe new schedule replaces the plan of record (POR).
  • CThe project remains locked until you manually unlock it.
  • DThe Schedule from Finish Date check box is selected by default.

How the community answered

(25 responses)
  • A
    12% (3)
  • B
    80% (20)
  • C
    4% (1)
  • D
    4% (1)