Question
How do projects differ from programs? (Choose three)
Options
- AOnly projects can have staff members.
- BPrograms cannot be financially enabled.
- CPrograms can have non-milestone tasks.
- DOnly projects can apply a work breakdown structure (WBS).
- EOnly programs can be opened with read/write access in a scheduler.