CAT-241 · Question #58

In CA Clarity PPM, you use the Create Task page to define all levels of a work breakdown structure (WBS). Before you can save a new task, which information must you supply? (Choose three)

The correct answer is A. Name D. Start Date E. Finish Date. See the full explanation below for the reasoning.

Question

In CA Clarity PPM, you use the Create Task page to define all levels of a work breakdown structure (WBS). Before you can save a new task, which information must you supply? (Choose three)

Options

  • AName
  • BStatus
  • CDuration
  • DStart Date
  • EFinish Date

How the community answered

(45 responses)
  • A
    82% (37)
  • B
    11% (5)
  • C
    7% (3)