CA_Technologies
CAT-241 · Question #50
When you use the Assign Resources page to assign a new resource to a project, you notice a resource that is no longer available for your project. You are unable to remove the resource because it has…
The correct answer is D. Click Replace and assign another resource to take on the remaining work from the original. See the full explanation below for the reasoning.
Question
When you use the Assign Resources page to assign a new resource to a project, you notice a resource that is no longer available for your project. You are unable to remove the resource because it has already booked actuals for a task. Which option is available to you?
Options
- ARemove the resource from your team and then remove the resource.
- BDeactivate the resource and delete the resource when the project is completed.
- CSet the Estimated Time to Complete (ETC) to zero and then remove the resource.
- DClick Replace and assign another resource to take on the remaining work from the original
How the community answered
(53 responses)- A2% (1)
- B11% (6)
- C6% (3)
- D81% (43)
Community Discussion
No community discussion yet for this question.