CA_Technologies
CAT-241 · Question #48
Sue White is a project owner and wants to track the Total Planned Cost ($350,000) and Total Planned Benefit ($400,000) because she will need to compare the actual totals at the end of the project to…
The correct answer is B. Use the Budget subpage to capture the data as totals because this is all the detail she needs. See the full explanation below for the reasoning.
Question
Sue White is a project owner and wants to track the Total Planned Cost ($350,000) and Total Planned Benefit ($400,000) because she will need to compare the actual totals at the end of the project to the planned totals. She does not need to break these totals down further. Which statement describes how she can best make this comparison?
Options
- ACreate custom attributes to hold the values.
- BUse the Budget subpage to capture the data as totals because this is all the detail she needs.
- CEnter the information in her work breakdown structure (WBS) under tasks identified as Planned
- DCalculate the monthly planned cost and monthly planned benefit by resource roles and then use
How the community answered
(27 responses)- A11% (3)
- B70% (19)
- C4% (1)
- D15% (4)
Community Discussion