Why does a resource manager use the allocation segments functionality when staffing a project with resources?

The correct answer is D. To represent a resource's variable availability to the project. See the full explanation below for the reasoning.

Question

Why does a resource manager use the allocation segments functionality when staffing a project with resources?

Options

  • ATo represent the actuals to date
  • BTo represent a part-time employee
  • CTo assign actuals to resources on projects
  • DTo represent a resource's variable availability to the project

How the community answered

(49 responses)
  • A
    2% (1)
  • B
    6% (3)
  • C
    10% (5)
  • D
    82% (40)