CAT-241 · Question #15

You have developed a new process and transported it to a production environment using XML Open Gateway (XOG). To make the process operational, which step do you need to perform?

The correct answer is D. Validate and activate the process. See the full explanation below for the reasoning.

Question

You have developed a new process and transported it to a production environment using XML Open Gateway (XOG). To make the process operational, which step do you need to perform?

Options

  • AChange Mode to Active.
  • BValidate the process only.
  • CRun the Execute a Process job.
  • DValidate and activate the process.

How the community answered

(64 responses)
  • A
    8% (5)
  • B
    16% (10)
  • C
    3% (2)
  • D
    73% (47)