nerdexam
CompTIACompTIA

CAS-005 · Question #171

CAS-005 Question #171: Real Exam Question with Answer & Explanation

The correct answer is D: RACI matrix. A RACI matrix is used to define and track roles and responsibilities in a project by identifying who is Responsible, Accountable, Consulted, and Informed for each task or phase. It’s the best tool for the project manager to manage role assignments throughout the deployment life c

Submitted by krish.m· Mar 6, 2026Governance, Risk, and Compliance

Question

An organization plans to deploy new software. The project manager compiles a list of roles that will be involved in different phases of the deployment life cycle. Which of the following should the project manager use to track these roles?

Options

  • ACMDB
  • BRecall tree
  • CITIL
  • DRACI matrix

Explanation

A RACI matrix is used to define and track roles and responsibilities in a project by identifying who is Responsible, Accountable, Consulted, and Informed for each task or phase. It’s the best tool for the project manager to manage role assignments throughout the deployment life cycle.

Community Discussion

No community discussion yet for this question.

Full CAS-005 PracticeBrowse All CAS-005 Questions