CAS-003 · Question #387
During the deployment of a new system, the implementation team determines that APIs used to integrate the new system with a legacy system are not functioning properly Further investigation shows…
The correct answer is B. Security requirements traceability matrix. Security Requirements Traceability Matrix (SRTM): Matrix documenting the system’s agreed upon security requirements derived from all sources, the security features’ implementation details and schedule, and the resources required for
Question
During the deployment of a new system, the implementation team determines that APIs used to integrate the new system with a legacy system are not functioning properly Further investigation shows there is a misconfigured encryption algorithm used to secure data transfers between systems. Which of the following should the project manager use to determine the source of the defined algorithm in use?
Options
- ACode repositories.
- BSecurity requirements traceability matrix.
- CSoftware development life cycle.
- DData design diagram.
- ERoles matrix.
- FImplementation guide.
How the community answered
(66 responses)- A5% (3)
- B82% (54)
- C2% (1)
- D11% (7)
- F2% (1)
Explanation
Security Requirements Traceability Matrix (SRTM): Matrix documenting the system’s agreed upon security requirements derived from all sources, the security features’ implementation details and schedule, and the resources required for