PMIPMI
CAPM · Question #6
CAPM Question #6: Real Exam Question with Answer & Explanation
The correct answer is B: Because every project is unique and not every tool, technique, input, or output identified in the PMBOK Guide is required. See the full explanation below for the reasoning.
Project Management Fundamentals and Core Concepts
Question
Why is tailoring required in a project?
Options
- ABecause a one-size-fits-all approach avoids complications and saves time
- BBecause every project is unique and not every tool, technique, input, or output identified in the PMBOK Guide is required
- CBecause tailoring allows us to identify the techniques, procedures, and system practices used by those on the project
- DProject managers should apply every process in the PMBOK Guide to the project, so tailoring is not required
Topics
#Project Tailoring#Project Uniqueness#PMBOK Guide Application#Process Adaptation
Community Discussion
No community discussion yet for this question.