nerdexam
PMIPMI

CAPM · Question #406

CAPM Question #406: Real Exam Question with Answer & Explanation

The correct answer is D: A mix of them. See the full explanation below for the reasoning.

Adaptive Frameworks/Methodologies

Question

A project manager was assigned to a project with high uncertainty. What is the recommended method to calculate the project budget?

Options

  • ADetailed estimation
  • BLightweight estimation
  • CParametric estimation
  • DA mix of them

Topics

#Project budgeting#Estimation techniques#High uncertainty#Adaptive planning

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions