PMIPMI
CAPM · Question #406
CAPM Question #406: Real Exam Question with Answer & Explanation
The correct answer is D: A mix of them. See the full explanation below for the reasoning.
Adaptive Frameworks/Methodologies
Question
A project manager was assigned to a project with high uncertainty. What is the recommended method to calculate the project budget?
Options
- ADetailed estimation
- BLightweight estimation
- CParametric estimation
- DA mix of them
Topics
#Project budgeting#Estimation techniques#High uncertainty#Adaptive planning
Community Discussion
No community discussion yet for this question.