nerdexam
PMI

CAPM · Question #406

A project manager was assigned to a project with high uncertainty. What is the recommended method to calculate the project budget?

Sign in or unlock CAPM to reveal the answer and full explanation for question #406. The question stem and answer options stay visible for context.

Adaptive Frameworks/Methodologies

Question

A project manager was assigned to a project with high uncertainty. What is the recommended method to calculate the project budget?

Options

  • ADetailed estimation
  • BLightweight estimation
  • CParametric estimation
  • DA mix of them

Unlock CAPM to see the answer

You've previewed enough free CAPM questions. Unlock CAPM for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Project budgeting#Estimation techniques#High uncertainty#Adaptive planning
Full CAPM Practice