nerdexam
PMIPMI

CAPM · Question #404

CAPM Question #404: Real Exam Question with Answer & Explanation

The correct answer is B: When the project objectives have been reached. See the full explanation below for the reasoning.

Project Management Fundamentals and Core Concepts

Question

When can we say that a project is completed?

Options

  • AWhen the planned time duration is completed
  • BWhen the project objectives have been reached
  • CWhen the project manager has left the team
  • DWhen the project team decides to stop the work on the project

Topics

#Project completion#Project objectives#Project closure

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions