nerdexam
PMI

CAPM · Question #404

When can we say that a project is completed?

The correct answer is B. When the project objectives have been reached. By definition, a project is a temporary endeavor undertaken to create a unique product, service, or result. A project is considered complete when its objectives have been achieved - the defined scope has been delivered, and the project's purpose has been fulfilled. Elapsed planne

Project Management Fundamentals and Core Concepts

Question

When can we say that a project is completed?

Options

  • AWhen the planned time duration is completed
  • BWhen the project objectives have been reached
  • CWhen the project manager has left the team
  • DWhen the project team decides to stop the work on the project

How the community answered

(31 responses)
  • A
    3% (1)
  • B
    94% (29)
  • C
    3% (1)

Explanation

By definition, a project is a temporary endeavor undertaken to create a unique product, service, or result. A project is considered complete when its objectives have been achieved - the defined scope has been delivered, and the project's purpose has been fulfilled. Elapsed planned time (A) does not guarantee objectives were met. A project manager leaving (C) is a personnel change, not a completion criterion. The team deciding to stop (D) could represent project cancellation, not successful completion. Successful project completion is always tied to achieving the defined objectives.

Topics

#Project completion#Project objectives#Project closure

Community Discussion

No community discussion yet for this question.

Full CAPM Practice