CAPM · Question #404
When can we say that a project is completed?
The correct answer is B. When the project objectives have been reached. By definition, a project is a temporary endeavor undertaken to create a unique product, service, or result. A project is considered complete when its objectives have been achieved - the defined scope has been delivered, and the project's purpose has been fulfilled. Elapsed planne
Question
Options
- AWhen the planned time duration is completed
- BWhen the project objectives have been reached
- CWhen the project manager has left the team
- DWhen the project team decides to stop the work on the project
How the community answered
(31 responses)- A3% (1)
- B94% (29)
- C3% (1)
Explanation
By definition, a project is a temporary endeavor undertaken to create a unique product, service, or result. A project is considered complete when its objectives have been achieved - the defined scope has been delivered, and the project's purpose has been fulfilled. Elapsed planned time (A) does not guarantee objectives were met. A project manager leaving (C) is a personnel change, not a completion criterion. The team deciding to stop (D) could represent project cancellation, not successful completion. Successful project completion is always tied to achieving the defined objectives.
Topics
Community Discussion
No community discussion yet for this question.