CAPM Question #391: Real Exam Question with Answer & Explanation

The correct answer is A: Need to lower production costs to remain competitive. See the full explanation below for the reasoning.

Project Management Fundamentals and Core Concepts

Question

Which of the following factors within a company cloud trigger the creation of a project?

Options

  • ANeed to lower production costs to remain competitive
  • BNeed to submit a warranty claim for a faulty product
  • CNeed to submit the monthly production report
  • DNeed to define next month's production goals

Topics

#Project initiation#Project triggers#Organizational factors#Operations vs. Projects

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions