CAPM · Question #391
CAPM Question #391: Real Exam Question with Answer & Explanation
The correct answer is A: Need to lower production costs to remain competitive. See the full explanation below for the reasoning.
Project Management Fundamentals and Core Concepts
Question
Which of the following factors within a company cloud trigger the creation of a project?
Options
- ANeed to lower production costs to remain competitive
- BNeed to submit a warranty claim for a faulty product
- CNeed to submit the monthly production report
- DNeed to define next month's production goals
Topics
#Project initiation#Project triggers#Organizational factors#Operations vs. Projects