CAPM · Question #348
Which of the following is least influenced by a project manager, according to the project manager's sphere of influence?
The correct answer is D. Stakeholders. According to PMBOK's concept of the project manager's sphere of influence, the PM has the greatest direct authority over the project team, which they manage day-to-day. Sponsors and steering committees are engaged through formal governance and communication channels, giving the…
Question
Options
- ASponsors
- BProject team
- CSteering committees
- DStakeholders
How the community answered
(50 responses)- A4% (2)
- B6% (3)
- C2% (1)
- D88% (44)
Explanation
According to PMBOK's concept of the project manager's sphere of influence, the PM has the greatest direct authority over the project team, which they manage day-to-day. Sponsors and steering committees are engaged through formal governance and communication channels, giving the PM meaningful - though less direct - influence. Stakeholders as a broad category, especially external or peripheral ones, operate largely outside the PM's direct authority. Their interests, behaviors, and decisions are influenced through engagement and communication rather than authority, making them the group over which the PM has the least influence.
Topics
Community Discussion
No community discussion yet for this question.