PMIPMI
CAPM · Question #298
CAPM Question #298: Real Exam Question with Answer & Explanation
The correct answer is D: 0-25%. See the full explanation below for the reasoning.
Adaptive Frameworks/Methodologies
Question
An adaptive team schedules 20 story points in the upcoming sprint. Historically, the team completes 25 story points on average per sprint. Each sprint is two weeks, and there is one day of float. What is the likelihood the team will complete all 20 story points in the upcoming sprint?
Options
- A50-75%
- B25-50%
- C75-100%
- D0-25%
Topics
#Agile Metrics#Team Velocity#Sprint Planning#Risk Management
Community Discussion
No community discussion yet for this question.