nerdexam
PMIPMI

CAPM · Question #298

CAPM Question #298: Real Exam Question with Answer & Explanation

The correct answer is D: 0-25%. See the full explanation below for the reasoning.

Adaptive Frameworks/Methodologies

Question

An adaptive team schedules 20 story points in the upcoming sprint. Historically, the team completes 25 story points on average per sprint. Each sprint is two weeks, and there is one day of float. What is the likelihood the team will complete all 20 story points in the upcoming sprint?

Options

  • A50-75%
  • B25-50%
  • C75-100%
  • D0-25%

Topics

#Agile Metrics#Team Velocity#Sprint Planning#Risk Management

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions