nerdexam
PMI

CAPM · Question #278

Question stem partially visible, relates to 'process?'

The correct answer is A. Increased support and minimized resistance from stakeholders. The key benefit of the Manage Stakeholder Engagement process is increased support and minimized resistance from stakeholders (A). By actively engaging stakeholders-addressing their concerns, resolving issues, and fostering collaboration-the project manager builds buy-in and reduc

Project Management Fundamentals and Core Concepts

Question

Question stem partially visible, relates to 'process?'

Options

  • AIncreased support and minimized resistance from stakeholders
  • BIncreased performance of the project team
  • CMaintained stakeholder satisfaction because costs and scope are under control
  • DUpdated project documents as requested by stakeholders

How the community answered

(39 responses)
  • A
    92% (36)
  • B
    5% (2)
  • D
    3% (1)

Explanation

The key benefit of the Manage Stakeholder Engagement process is increased support and minimized resistance from stakeholders (A). By actively engaging stakeholders-addressing their concerns, resolving issues, and fostering collaboration-the project manager builds buy-in and reduces opposition, which directly improves the likelihood of project success. Increased team performance (B) is a benefit of the Develop Team process, not stakeholder management. Maintaining satisfaction through cost and scope control (C) describes project monitoring outcomes, not an engagement process benefit. Updating project documents at stakeholder request (D) is an activity that may occur, but it is not a key benefit-it describes a task, not an outcome of the engagement process.

Topics

#Stakeholder engagement#Resistance management#Project success factors#Stakeholder management

Community Discussion

No community discussion yet for this question.

Full CAPM Practice