The correct answer is B: Physical location tailoring. See the full explanation below for the reasoning.

Project Management Fundamentals and Core Concepts

Question

A project manager of a civil construction project is trying to understand the local laws. What example of tailoring procurement could this best be described as?

Options

  • ACompliance and governance
  • BPhysical location tailoring
  • CComplexity of procurement
  • DAvailability of contractors

Topics

#Project Tailoring#Procurement Management#Regulatory Compliance#External Environmental Factors (EEFs)

Community Discussion