The correct answer is D: Reduces project cost by use of modern technologies allowing seamless team collaboration. See the full explanation below for the reasoning.

Project Management Fundamentals and Core Concepts

Question

What is a key benefit of using virtual project teams?

Options

  • AEnsures appropriate behavior, security, and the protection of proprietary information
  • BReduces the risk of conflict due to interpersonal communications and other interactions
  • CAssures that all team members have a clear and common understanding of the project
  • DReduces project cost by use of modern technologies allowing seamless team collaboration

Topics

#Virtual Teams#Team Management#Cost Management#Project Resources