nerdexam
PMIPMI

CAPM · Question #132

CAPM Question #132: Real Exam Question with Answer & Explanation

The correct answer is C: Formal communication. See the full explanation below for the reasoning.

Project Management Fundamentals and Core Concepts

Question

A project team submits a weekly progress report to the project manager. The project manager consolidates the same report and sends a complete progress report to the stakeholders. What is this an example of?

Options

  • AInformal communication
  • BInternal communication
  • CFormal communication
  • DHorizontal communication

Topics

#Communication Management#Formal Communication#Progress Reporting#Stakeholder Communication

Community Discussion

No community discussion yet for this question.

Full CAPM PracticeBrowse All CAPM Questions