PMIPMI
CAPM · Question #132
CAPM Question #132: Real Exam Question with Answer & Explanation
The correct answer is C: Formal communication. See the full explanation below for the reasoning.
Project Management Fundamentals and Core Concepts
Question
A project team submits a weekly progress report to the project manager. The project manager consolidates the same report and sends a complete progress report to the stakeholders. What is this an example of?
Options
- AInformal communication
- BInternal communication
- CFormal communication
- DHorizontal communication
Topics
#Communication Management#Formal Communication#Progress Reporting#Stakeholder Communication
Community Discussion
No community discussion yet for this question.