The correct answer is C: Project Integration Management is the responsibility of the project manager. See the full explanation below for the reasoning.

Project Management Fundamentals and Core Concepts

Question

Which of these is true of project integration management?

Options

  • AProject Integration Management is mandatory and more effective in larger projects
  • BProject Integration Management and expert judgment are mutually exclusive
  • CProject Integration Management is the responsibility of the project manager
  • DProject Integration Management excludes the triple constraints if cost performance index (CPI) equals zero

Topics

#Project Integration Management#Project Manager Role#PMI PMBOK#Core Project Management