You are working as a project manager in your organization. You are nearing the final stages of project execution and looking towards the final risk monitoring and controlling activities. For your proj

The correct answer is C. Requested changes. According to PMBOK, outputs of the Risk Monitoring and Control process include: Risk Register updates, Recommended corrective and preventive actions, Requested Changes (C), and Organizational Process Asset updates. 'Requested Changes' is the correct answer - when risk events occu

Security and Privacy Governance, Risk Management, and Compliance Program

Question

You are working as a project manager in your organization. You are nearing the final stages of project execution and looking towards the final risk monitoring and controlling activities. For your project archives, which one of the following is an output of risk monitoring and control?

Options

  • AQuantitative risk analysis
  • BQualitative risk analysis
  • CRequested changes
  • DRisk audits

How the community answered

(29 responses)
  • B
    3% (1)
  • C
    93% (27)
  • D
    3% (1)

Explanation

According to PMBOK, outputs of the Risk Monitoring and Control process include: Risk Register updates, Recommended corrective and preventive actions, Requested Changes (C), and Organizational Process Asset updates. 'Requested Changes' is the correct answer - when risk events occur or the risk register changes, formal change requests are generated to adjust the project baseline. Quantitative (A) and Qualitative (B) risk analysis are separate planning processes, not outputs of monitoring. Risk Audits (D) are a tool and technique used within the monitoring process, not an output of it.