You are the project manager for your company and a new change request has been approved for your project. This change request, however, has introduced several new risks to the project. You have…

The correct answer is A. Risk register. The Risk Register is the central document used to record all identified risks, their characteristics, analysis results (probability, impact), and planned risk responses - including mitigation strategies. It is a living document updated throughout the project as risks are…

Security and Privacy Governance, Risk Management, and Compliance Program

Question

You are the project manager for your company and a new change request has been approved for your project. This change request, however, has introduced several new risks to the project. You have communicated these risk events and the project stakeholders understand the possible effects these risks could have on your project. You elect to create a mitigation response for the identified risk events. Where will you record the mitigation response?

Options

  • ARisk register
  • BRisk log
  • CRisk management plan
  • DProject management plan

How the community answered

(19 responses)
  • A
    89% (17)
  • C
    5% (1)
  • D
    5% (1)

Explanation

The Risk Register is the central document used to record all identified risks, their characteristics, analysis results (probability, impact), and planned risk responses - including mitigation strategies. It is a living document updated throughout the project as risks are identified, analyzed, and responded to. The Risk Management Plan describes the methodology and approach for how risks will be managed (processes, roles, timing), not the specific risks or responses. The Project Management Plan is a higher-level document; specific risk details belong in the Risk Register.

Topics

#Risk Management#Risk Register#Mitigation Response#Project Management

Community Discussion