Question

You are the project manager for your company and a new change request has been approved for your project. This change request, however, has introduced several new risks to the project. You have communicated these risk events and the project stakeholders understand the possible effects these risks could have on your project. You elect to create a mitigation response for the identified risk events. Where will you record the mitigation response?

Options

  • ARisk register
  • BRisk log
  • CRisk management plan
  • DProject management plan

Unlock CAP to see the answer

You've previewed enough free CAP questions. Unlock CAP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Topics

#Risk Management#Risk Register#Mitigation Response#Project Management
Full CAP PracticeBrowse All CAP Questions