CAP · Question #75
You are the project manager of the GHY project for your organization. You are working with your project team to begin identifying risks for the project. As part of your preparation for identifying the
The correct answer is C. Procurement management plan. According to the PMBOK Guide, the Identify Risks process uses inputs from the project management plan (including the cost management plan, quality management plan, schedule management plan, HR management plan, and scope/schedule/cost baselines), project documents (including the s
Question
You are the project manager of the GHY project for your organization. You are working with your project team to begin identifying risks for the project. As part of your preparation for identifying the risks within the project you will need eleven inputs for the process. Which one of the following is NOT an input to the risk identification process?
Options
- ACost management plan
- BQuality management plan
- CProcurement management plan
- DStakeholder register
How the community answered
(60 responses)- A2% (1)
- B7% (4)
- C88% (53)
- D3% (2)
Explanation
According to the PMBOK Guide, the Identify Risks process uses inputs from the project management plan (including the cost management plan, quality management plan, schedule management plan, HR management plan, and scope/schedule/cost baselines), project documents (including the stakeholder register), enterprise environmental factors, and organizational process assets. The Procurement Management Plan is not listed as a direct input to risk identification; it is used primarily in the Plan Procurement Management and Conduct Procurements processes. The cost management plan, quality management plan, and stakeholder register are all valid inputs.
Topics
Community Discussion
No community discussion yet for this question.