(ISC)2(ISC)2
CAP · Question #62
CAP Question #62: Real Exam Question with Answer & Explanation
The correct answer is A: Mary will utilize the schedule controls and the nature of the schedule for the quantitative. See the full explanation below for the reasoning.
Security and Privacy Governance, Risk Management, and Compliance Program
Question
Mary is the project manager for the BLB project. She has instructed the project team to assemble, to review the risks. She has included the schedule management plan as an input for the quantitative risk analysis process. Why is the schedule management plan needed for quantitative risk analysis?
Options
- AMary will utilize the schedule controls and the nature of the schedule for the quantitative
- BMary will schedule when the identified risks are likely to happen and affect the project
- CMary will utilize the schedule controls to determine how risks may be allowed to change the
- DMary will use the schedule management plan to schedule the risk identification meetings
Topics
#Risk Management#Quantitative Risk Analysis#Schedule Management#Risk Analysis Inputs
Community Discussion
No community discussion yet for this question.