nerdexam
(ISC)2

CAP · Question #59

You are the project manager of the GGG project. You have completed the risk identification process for the initial phases of your project. As you begin to document the risk events in the risk register

The correct answer is B. Risk potential responses. When initially creating the risk register during the Identify Risks process, the PMBOK Guide specifies that potential responses may be identified and recorded alongside each risk event. These are preliminary, not finalized responses - formal risk response planning comes later in

Security and Privacy Governance, Risk Management, and Compliance Program

Question

You are the project manager of the GGG project. You have completed the risk identification process for the initial phases of your project. As you begin to document the risk events in the risk register what additional information can you associate with the identified risk events?

Options

  • ARisk schedule
  • BRisk potential responses
  • CRisk cost
  • DRisk owner

How the community answered

(32 responses)
  • A
    6% (2)
  • B
    88% (28)
  • C
    3% (1)
  • D
    3% (1)

Explanation

When initially creating the risk register during the Identify Risks process, the PMBOK Guide specifies that potential responses may be identified and recorded alongside each risk event. These are preliminary, not finalized responses - formal risk response planning comes later in the Plan Risk Responses process. The risk register at this stage typically includes the list of identified risks, potential causes, potential responses, and risk categories. Risk owners (D) and risk costs (C) are typically assigned and quantified later, during risk analysis and response planning, not during initial identification.

Topics

#Risk Management Process#Risk Register#Risk Identification#Risk Response Planning

Community Discussion

No community discussion yet for this question.

Full CAP Practice