(ISC)2(ISC)2
CAP · Question #54
CAP Question #54: Real Exam Question with Answer & Explanation
The correct answer is B: Procurement management plan. See the full explanation below for the reasoning.
Security and Privacy Governance, Risk Management, and Compliance Program
Question
You are the project manager of the GHY project for your organization. You are working with your project team to begin identifying risks for the project. As part of your preparation for identifying the risks within the project you will need eleven inputs for the process. Which one of the following is NOT an input to the risk identification process?
Options
- ACost management plan
- BProcurement management plan
- CStakeholder register
- DQuality management plan
Topics
#Risk Management Process#Risk Identification#Project Management#Information Security Governance
Community Discussion
No community discussion yet for this question.