CAP · Question #54
You are the project manager of the GHY project for your organization. You are working with your project team to begin identifying risks for the project. As part of your preparation for identifying…
The correct answer is B. Procurement management plan. According to the PMBOK Guide, the Identify Risks process inputs include the risk management plan, cost management plan, schedule management plan, quality management plan, human resource management plan, scope baseline, activity cost estimates, activity duration estimates…
Question
You are the project manager of the GHY project for your organization. You are working with your project team to begin identifying risks for the project. As part of your preparation for identifying the risks within the project you will need eleven inputs for the process. Which one of the following is NOT an input to the risk identification process?
Options
- ACost management plan
- BProcurement management plan
- CStakeholder register
- DQuality management plan
How the community answered
(34 responses)- A3% (1)
- B88% (30)
- C3% (1)
- D6% (2)
Explanation
According to the PMBOK Guide, the Identify Risks process inputs include the risk management plan, cost management plan, schedule management plan, quality management plan, human resource management plan, scope baseline, activity cost estimates, activity duration estimates, stakeholder register, project documents, and enterprise environmental factors/organizational process assets. The Procurement Management Plan is not listed as a direct input to the Identify Risks process. While procurement risks can exist, the procurement management plan itself is not among the standard inputs to risk identification.