nerdexam
(ISC)2

CAP · Question #46

You work as a project manager for BlueWell Inc. You are currently working with the project stakeholders to identify risks in your project. You understand that the qualitative risk assessment and…

The correct answer is D. Evaluate the bias towards the risk events and correct the assessment accordingly. Qualitative risk analysis is inherently subjective and can be skewed by the risk attitudes (risk-averse vs. risk-tolerant) and cognitive biases of participants. The correct approach is to evaluate the bias each participant brings to their risk assessments and then correct the…

Security and Privacy Governance, Risk Management, and Compliance Program

Question

You work as a project manager for BlueWell Inc. You are currently working with the project stakeholders to identify risks in your project. You understand that the qualitative risk assessment and analysis can reflect the attitude of the project team and other stakeholders to risk. Effective assessment of risk requires management of the risk attitudes of the participants. What should you, the project manager, do with assessment of identified risks in consideration of the attitude and bias of the participants towards the project risk?

Options

  • ADocument the bias for the risk events and communicate the bias with management
  • BEvaluate and document the bias towards the risk events
  • CEvaluate the bias through SWOT for true analysis of the risk events
  • DEvaluate the bias towards the risk events and correct the assessment accordingly

How the community answered

(38 responses)
  • A
    13% (5)
  • B
    8% (3)
  • C
    3% (1)
  • D
    76% (29)

Explanation

Qualitative risk analysis is inherently subjective and can be skewed by the risk attitudes (risk-averse vs. risk-tolerant) and cognitive biases of participants. The correct approach is to evaluate the bias each participant brings to their risk assessments and then correct the assessments accordingly to ensure they reflect reality rather than personal disposition. Simply documenting the bias (options A and B) without correcting it leaves the analysis flawed. Using SWOT (option C) is a risk identification tool, not a bias-correction mechanism.

Topics

#Risk Management#Qualitative Risk Assessment#Bias Mitigation#Project Management

Community Discussion

No community discussion yet for this question.

Full CAP Practice